Nursing Homes Are In The Dark As More Utilities Cut Power To Prevent Wildfires

When powerful wind gusts created threatening wildfire conditions one day near Boulder, Colorado, the state’s largest utility cut power to 52,000 homes and businesses — including Frasier, an assisted living and skilled nursing facility.

It was the first time Xcel Energy proactively switched off electricity in Colorado as a wildfire prevention tool, according to a company official. The practice, also known as public safety power shut-offs, has taken root in Caalifornia and is spreading elsewhere as a way to keep downed and damaged power lines from sparking blazes and fueling the West’s more frequent and intense wildfires.

In Boulder, Frasier staff and residents heard about the planned outage from news reports. A Frasier official called the utility to confirm and was initially told the home’s power would not be affected. The utility then called back to say the home’s power would be cut, after all, said Tomas Mendez, Frasier’s vice president of operations. The home had just 75 minutes before Xcel Energy shut off the lights on April 6.

The staff rushed to prepare the 20-acre campus home to nearly 500 residents. Generators kept running the oxygen machines, most refrigerators and freezers, hallway lights, and Wi-Fi for phones and computers. But the heating system and some lights stayed off as the overnight temperature dipped into the 30s.

“These are the folks that depend on us for everything: meals, care, and medications,” he said.

Not knowing when electricity would be restored, even during the second day of the crisis, added stress and additional costs, including refueling two generators.

“While we were lucky there were no injuries or significant issues, it’s likely that these could occur with power outages – expected or unexpected. This puts all residents at risk,” Mendez said.

Power was restored to Frasier after 28 hours. During the shut-off, staff tended to nursing home and assisted living residents, many with dementia, Mendez said.

“We need to prioritize these residents so that, when the power goes out, they are the first to have it restored,” stated David Dosa, Chief of Geriatrics and Professor of Medicine at UMass Chan Medical School in Worcester, Massachusetts.

When the forecast called for wind gusts of up to 100 mph on April 6, Xcel Energy implemented a public safety power shut-off. Nearly 275,000 customers were without power from the windstorm.

Officials had adapted after the Marshall Fire killed two people and destroyed or damaged more than 1,000 homes in Boulder and the neighboring communities of Louisville and Superior two and a half years ago. Two fires converged to form that blaze, and electricity from an Xcel Energy power line that detached from its pole in hurricane-force winds ”was the most probable cause” of one of them.

“A preemptive shutdown is scary because you don’t have an end in mind. They don’t tell you the duration,” said Jenny Albertson, director of quality and regulatory affairs for the Colorado Health Care Association and Center for Assisted Living.

Under federal guidelines, nursing homes must have disaster response plans that include emergency power or building evacuation. Those plans don’t necessarily include contingencies for public safety power shut-offs, which have increased in the past five years but are still relatively new. And nursing homes in the West are rushing to catch up.

In California, a more stringent law to bring emergency power in nursing homes up to code is expected by the California Association of Health Facilities to cost over $1 billion. But the state has not allocated any funding for these facilities to comply, said Corey Egel, the association’s director of public affairs. The association is asking state officials to delay implementation of the law for five years, to Jan. 1, 2029.

Most nursing homes operate on a razor’s edge in terms of federal reimbursement, Dosa said, and it’s incredibly expensive to retrofit an old building to keep up with new regulations.

Bryant said Xcel Energy’s prioritization plan for health facilities specifies not whether their electricity will be turned off during a public safety power shut-off — but how quickly it will be restored.

Julie Soltis, Frasier’s director of communications, said the home had plenty of blankets, flashlights, and batteries during the outage. But Frasier plans to invest in headlamps for caregivers, and during a town hall meeting, independent living residents were encouraged to purchase their backup power for mobile phones and other electronics, she said.

Soltis hopes her facility is spared during the next public safety power shut-off or at least given more time to respond.

“With weather and climate change, this is not the last time this will happen,” she said.

Related posts

Zac Efron Says He Is Okay After Brief Hospitalization From Swimming

Lynda

Weeping Families Mourn Thai School Bus Crash Victims

Lynda

Trayon White Sr. Arrested On Bribery Charge

Lynda

Simon Cowell Gives Credit To son Eric For Saving Him From ‘Downward Spiral’

Lynda

Shane Filan One of Westlife Brothers Faces €23million Bankruptcy, Fears For His Kids Well-Being

Lynda

Series Of Mass Shootings Across The US Mark The First Weekend of Summer

Lynda